This is a list of the schedule changes for MC-F.
.TS
center tab(:);
l l l.
Date :Working Proto :Production parts

12/84 :3/85 :7/85
1/85 :6/85 :11/85
4/85 :7/85 :11/85
5/85 :9/85 :5/86
.TE
.DE

This lists the slips of having the pick and place machine to the point
that it can place the parts on 80 boards.  It also has the date for being
ready for production.

.DF
.TS
center tab(:);
l l l.
Date :80 Boards :Production

8/84 :3/85 :9/85
12/84 :4/85 :10/85
2/85 :5/85 :10/85
5/85 :6/85 :11/85
.TE
.DE