6/1/86

Rob Horning

I was only in about 2 days last week.

The Math PC board tapes were sent to Loveland on Thursday morning.  They
told me that they should start the build on Wednesday.  They said that it
takes about 9 days to get boards after the boards are started, but that
they often have to restart the run.

Toshiba said that they send me 150 1 Mbit DRAM's on Friday.  They did not
have a weigh bill number.  There may be a problem with getting the next
1500 parts that we have on order.  We may have to get together with the
Bobcat-32 people to decide how to allocate parts.

I received some 25 ns SRAM's from a start up called Vitelic.  I do not know
anything about the company and have not looked at the parts yet.

I have started the ERS for the Math board.  I would like to get a rough draft
of the documentation done while the design is still fresh in my head.
 